A feed-in tariff is a policy paying solar owners a fixed rate for each kilowatt-hour they send to the grid. Key aspects include rate, contract length, availability, net metering comparison, types, payment calculation, eligibility requirements, tax treatment, and funding and transferability. You receive payment under this arrangement through a contract that sets the rate and the number of years it applies, often 10 to 25. Rates usually depend on system size and installation date, and availability varies by country, region and utility. Many programs have closed to new applicants or been replaced by other schemes, so the rules in force today may differ from earlier years. Information about solar companies in DE shows how the German model shaped this approach and influenced programs elsewhere. This article explains rate levels, contract length, availability and how a feed-in tariff differs from net metering, where you earn bill credits instead of a fixed payment.
Key Takeaways
- A feed-in tariff (FIT) pays you a fixed, guaranteed rate for your solar energy exports.
- Export rates typically range from 2 to 15 cents per kWh, depending on your local utility.
- Net metering credits you at retail rates, while a FIT pays a specific contractual rate.
- Most FIT contract terms span 15 to 25 years to provide predictable long-term revenue.
- Rate degression can reduce your payout by 1 to 10 percent per period for new applicants.
How Much Per kWh Will a Feed-in Tariff Pay for Your Exported Solar Electricity?
The amount you receive for your exported solar electricity through a feed-in tariff (FIT) depends on your specific utility and local regulations, with typical US export rates ranging from about 2 to 15 cents per kWh, while structures like California’s Net Billing Tariff often value exported energy at under 10 cents per kWh on average. Per the Database of State Incentives for Renewables and Efficiency, utility compensation for excess solar generation is frequently governed by state-specific net billing policies, which may credit exported electricity at a rate lower than the retail price of electricity.
| Compensation Model | Generation Basis | Revenue Scope |
|---|---|---|
| Gross Feed-in Tariff (FIT) | Total system production | Full output credited; separate purchase of household electricity |
| Export Feed-in Tariff (FIT) | Surplus energy only | Only excess energy sent to grid is compensated |
| Net Billing Tariff | Net surplus output | Utility-specific rates (often < retail price per kWh) |
Typical Solar Export Compensation Rates (Cents per kWh)
Gross FIT vs. Export FIT Payment Structures
The amount a feed-in tariff (FIT) will pay for your exported solar electricity depends on whether your program compensates you for your entire generation profile or only for the surplus energy you send to the grid. Under a gross FIT, you receive payment for every kilowatt-hour (kWh) your system generates, while you separately purchase the electricity your household consumes from the utility. Conversely, an export FIT only provides compensation for the energy you send back to the grid after your home has consumed what it needs.
Worked Example for a 7 kW System
If your system configuration requires you to send your production to the grid, the payout calculation is straightforward. A 7 kW system producing roughly 9,000 to 10,000 kWh per year earns about $450 per year at 5 cents per kWh if fully exported.
What Does a Premium FIT Add to the Export Rate?
A premium FIT provides a fixed financial bonus layered on top of the fluctuating market price of electricity. This mechanism is designed to provide greater revenue certainty compared to standard market-based export rates. The bonus is typically structured as follows:
- Market Price: The base rate determined by wholesale electricity demand.
- Premium Bonus: A guaranteed supplemental payment per kWh added to the market price.
- Total Revenue: The combined value, ensuring a higher floor for your exported energy.
How US Avoided-Cost Rates Compare
Typical US avoided-cost or export rates range from about 2 to 15 cents per kWh depending on utility and state. Because PURPA, enacted in 1978, is the closest US federal framework and requires utilities to buy from qualifying facilities at avoided cost, many programs lack the high-incentive pricing seen in early international models, such as when early German feed-in tariff rates in the 2000s exceeded 50 euro cents per kWh. Exported solar under export-rate structures such as a Net Billing Tariff is often valued at under 10 cents per kWh on average.
Review your utility’s specific interconnection agreement to verify if your generation requires a dedicated generation meter or a bidirectional meter to properly record your export totals.
Factors that influence your specific feed-in tariff compensation rate include:
- Time-of-use (TOU) pricing, where credits are higher during peak demand hours compared to off-peak periods.
- Interconnection agreement terms that dictate whether credits roll over monthly or expire at the end of each billing cycle.
- Utility ownership status, as municipal utilities and electric cooperatives often operate under different regulatory frameworks than investor-owned utilities.
- The presence of grid-stability requirements that may limit the amount of power your system is permitted to export back to the local network.

How Long a Feed-in Tariff Contract Lasts
The contract term for a feed-in tariff (FIT) represents the duration during which you are guaranteed a fixed payment for the renewable energy you export to the grid. Typical feed-in tariff (FIT) contract terms abroad run 15 to 25 years, providing a long-term, predictable revenue stream that helps offset the initial capital costs of your installation. By locking in a specific rate for this period, you remove much of the uncertainty associated with fluctuating market prices for electricity, ensuring that your investment maintains a stable return regardless of broader economic shifts.
| Contract Specification | Standard Duration | Strategic Financial Impact |
|---|---|---|
| Minimum Contract Term | 15 Years | Baseline period for primary equipment amortization |
| Maximum Contract Term | 25 Years | Optimized window for total lifecycle revenue capture |
| Regulatory Alignment | Variable | Matches anticipated operational lifespan of hardware |
| Revenue Predictability | Fixed Term | Mitigates long-term exposure to grid price volatility |
Typical Feed-in Tariff (FIT) Contract Terms (Years)
The duration of your agreement often interacts with the size of your system and the specific policy framework governing the program. According to the Solar Energy Industries Association, while federal policies provide a framework, contract lengths are primarily set by state regulators and typically align with the expected operational lifespan of solar equipment. Because these contracts are legally binding arrangements with a utility or grid operator, the length is typically non-negotiable once the application is approved and the system is commissioned. Understanding the timeline is crucial, as the amortization of your equipment cost must align with the guaranteed payment window. Consider the following factors when evaluating the longevity of your commitment:
- The total duration of the guaranteed purchase obligation from the utility.
- Whether the contract term is tied to the specific system hardware or remains with the property title upon sale.
- The specific milestone dates for initial commissioning required to activate the full length of the agreement.
- Regulatory provisions that define if the contract remains valid if the local utility structure changes ownership.
Review the specific expiration date of your offer to determine if the projected payback period for your equipment falls safely within the guaranteed payment window.
Key factors to consider when evaluating specific FIT contract offers include:
- Verification of whether the tariff rate includes annual inflation adjustments (CPI indexation).
- Assessment of early termination penalties or conditions for contract transfer during property resale.
- Confirmation of grid interconnection requirements that may impact long-term maintenance costs.
- Analysis of potential curtailment provisions that allow utility providers to limit energy exports during peak supply periods.
Is There a Feed-in Tariff for Solar Panels in the United States?
No, there is no nationwide federal feed-in tariff (FIT) for solar panels in the United States, though various mechanisms exist that function similarly to provide compensation for exported energy. While no single federal policy mandates a standard feed-in tariff (FIT), several frameworks and localized programs regulate how you are compensated for the electricity your solar array sends to the utility grid.
| Compensation Framework | Regulatory Origin | Primary Mechanism | Rate Structure Characteristics |
|---|---|---|---|
| PURPA (1978) | Federal (FERC) | Mandatory Utility Purchase | Avoided cost rate baseline |
| State-Level Standard Offers | State Legislation | Fixed-rate guarantee | Tiered by project scale |
| Utility-Specific Programs | Local Municipal/Regional | Proprietary Contracts | Predetermined, long-term stability |
| Market-Adjusting Tariffs | Regional Procurement | Competitive Bidding | Degression schedule based on capacity |
| Net Billing Tariffs | State Utility Commissions | Avoided cost/Value-based export | Dynamic valuation, lower than retail |
- PURPA (1978): This remains the closest federal framework. According to the Federal Energy Regulatory Commission, this act requires utilities to purchase power from qualifying small-scale renewable facilities at their avoided cost rate, which acts as a regulatory baseline rather than a traditional feed-in tariff.
- State-Level Standard Offers: Certain states implement specific programs, often tiered by system size, that function like a traditional feed-in tariff (FIT) to guarantee a fixed payment rate for renewable generation.
- Utility-Specific Programs: Many local municipal utilities or regional providers manage their own proprietary FIT programs that offer predetermined, long-term export rates for eligible renewable projects.
- Market-Adjusting Tariffs: Some regions utilize competitive procurement models where the export rate is adjusted based on capacity targets, often using a degression schedule to manage program participation.
- Net Billing Tariff Models: While distinct from a true feed-in tariff (FIT), many states have transitioned to structures like the Net Billing Tariff, where exported solar energy is valued at rates often under 10 cents per kWh on average.
Review your local utility’s interconnection agreement to determine if they offer a fixed-rate export program or if you are limited to the variable rates associated with a Net Billing Tariff.
Key considerations for residential and commercial solar owners when evaluating these compensation models include:
- Interconnection Requirements: Most utilities mandate specific technical reviews and grid-tie equipment standards before allowing export to the local network.
- Metering Infrastructure: You may need to upgrade to a bi-directional meter to accurately track electricity consumption versus production.
- Contract Duration: Fixed-rate tariffs often require signing multi-year power purchase agreements (PPAs) that lock in specific buy-back rates.
- System Sizing Limits: Many utility programs restrict the maximum array capacity eligible for compensation to ensure it aligns with historical on-site load requirements.
- Non-Transferability: Specific incentive agreements are frequently tied to the original account holder and may not automatically transfer to a new property owner.
Feed-in Tariff vs. Net Metering: Which Is Better for You?
A feed-in tariff (FIT) is a system of fixed, guaranteed payments for electricity exported to the grid, whereas net metering provides credits against your own household consumption, often valued at or near the retail rate. The core difference lies in how your utility treats the value of the energy your solar system generates relative to the energy you draw from the utility. Per the Department of Energy, net metering typically functions as a retail-rate credit mechanism to offset a consumer’s own electricity consumption, while feed-in tariffs generally provide a fixed, long-term contract rate for all energy produced regardless of whether the consumer uses it themselves.
| Feature | Net Metering | Feed-in Tariff (FIT) |
|---|---|---|
| Payment Basis | Retail rate credits | Fixed contractual export rate |
| Primary Goal | Offset personal energy costs | Revenue generation for exported power |
| Valuation | Variable, often 1:1 with retail | Predictable, set by contract |
| Metering | Bidirectional meter | Dedicated or bidirectional meter |
Net metering generally offers higher financial returns when you use your solar output to replace expensive retail-priced grid electricity, as most utilities value credits at your full retail rate. Conversely, a feed-in tariff (FIT) provides a steady, long-term revenue stream for all electricity you export, which is often more beneficial if your generation capacity significantly exceeds your household’s daily consumption. Under modern export-rate structures like a Net Billing Tariff, the value of your exported power frequently drops below 10 cents per kWh, making the consistency of a traditional FIT attractive for those prioritizing investment security over immediate retail-rate offsets.
Review your utility’s current monthly billing statements to see if your solar exports are credited at the full retail rate or if you have already been moved to an export-rate structure that requires a dedicated FIT comparison.
Consider these additional factors when evaluating which compensation structure better suits your specific solar installation:
- System Sizing Strategy: Net metering rewards smaller systems optimized to match household consumption, while feed-in tariffs favor larger, utility-scale arrays built for maximum production.
- Contractual Duration: Feed-in tariffs often lock in rates for 15 to 25 years, providing long-term price certainty that is rarely available under standard net metering policies.
- Administrative Requirements: Feed-in tariffs frequently require additional legal agreements and grid-impact studies compared to the standard interconnection process used for net metering.
- Regulatory Stability: Net metering programs are subject to frequent policy revisions by state utility commissions, whereas FIT agreements are typically protected by signed, binding contracts.
Why Feed-in Tariff Rates Drop Over Time and How Degression Affects New Applicants
Feed-in tariff rates drop over time due to degression, a policy mechanism designed to reduce the financial support provided to new participants as the cost of solar technology declines and project efficiency improves. By lowering the guaranteed payment per kilowatt-hour for subsequent applicants, regulators ensure that the feed-in tariff remains sustainable for the utility while preventing excessive subsidies for established technologies. Per the National Renewable Energy Laboratory, tariff degression schedules are designed to reflect the declining cost of solar technology, ensuring that subsidy levels remain proportional to falling capital expenditures rather than providing windfall profits to late-stage adopters. This systematic reduction helps align the export rate with the falling market costs of hardware and installation.
| Degression Driver | Impact on Tariff Reduction | Primary Economic Rationale |
|---|---|---|
| Technological Maturity | Gradual | Offsetting reduced hardware capital expenditure |
| Deployment Pace | Aggressive | Preventing market overheating and subsidy overspend |
| Capacity Thresholds | Step-wise | Balancing utility budget with scale-based efficiencies |
| ROI Policy Reviews | Periodic | Aligning incentive value with current market benchmarks |
Typical Rate Degression Range
When you apply for a new contract, the specific rate you receive is typically locked in based on the current schedule rather than the rates offered to earlier participants. The following factors often influence the intensity of this periodic adjustment:
- Technological maturity, where lower hardware costs justify a smaller incentive.
- Deployment pace, where rapid uptake triggers a faster reduction in the offered rate.
- Capacity thresholds, which trigger a stepped decline in the export rate once a certain volume of installations is reached.
- Policy review cycles, where administrative bodies evaluate the return on investment for the average system.
The standard rate degression for new participants is often 1 to 10 percent per period, depending on the program’s oversight and total capacity targets. Verify whether your local program utilizes a fixed calendar-based reduction or a capacity-triggered decline to determine the most advantageous time to submit your interconnection application.
Applicants should consider these practical implications when finalizing their solar integration strategy:
- Lock in current rates by submitting applications prior to the next scheduled regulatory review cycle.
- Monitor state-level policy announcements to identify upcoming capacity trigger events that may accelerate degression.
- Evaluate the internal rate of return against the specific degression tier applicable to your project’s installation date.
- Consult with local installers to confirm whether the utility applies the rate based on the application filing date or the final interconnection approval date.
Frequently Asked Questions
What is the difference between a gross, net, and premium solar feed-in tariff?
The difference between these models is how they value electricity: a gross FIT pays for all generation, an export FIT pays only for surplus sent to the grid, and a premium FIT adds a fixed bonus to the market price of your exported electricity.
How do I calculate how much a solar feed-in tariff will pay for my system?
You calculate your annual earnings by multiplying your exported kilowatt-hours by the tariff rate. For example, a 7 kW system producing 9,000 to 10,000 kWh per year would earn about $450 if fully exported at 5 cents per kWh, assuming your utility uses that specific export rate.
What requirements must my solar system meet to qualify for a feed-in tariff?
To qualify, you must typically install a bidirectional meter or a dedicated generation meter to accurately measure your exports. Programs often categorize systems by size, such as residential under 10 kW or commercial up to 1 MW, and may require compliance with local interconnection standards and long-term contracts.
Is income from a solar feed-in tariff taxable?
Yes, income from a solar feed-in tariff is generally considered taxable revenue, though tax status varies by jurisdiction. You should consult a local tax professional to determine how payments received under your long-term contract affect your specific personal or business tax liabilities.
Does a solar feed-in tariff contract transfer to the buyer if I sell my house?
Yes, a solar feed-in tariff contract often transfers to the homebuyer, though this depends on the specific terms of your agreement. Because these contracts typically run 15 to 25 years, they act as an asset tied to the property, providing the new owner with the same predictable revenue stream.